Why Networks? Splits decision-making cleanly into 3 separate steps: (1) Method/Logic β (2) Time β (3) Resources. Two modes: AOA (Activity on Arrow, traditional) vs. AON (Activity on Node, MS Project).
Core Network Elements
- Event Specific instant of commencement/completion (node). Types: Tail (starts activity; 1st = Initial), Head (ends activity; last = Final), Dual (all intermediate nodes). Linked as Predecessor/Successor.
- Activity Actual task consuming time & resources (arrow). Either Parallel (simultaneous/independent) or Serial (one after another).
- Dummy Dashed arrow consuming zero time and zero resources; used solely to maintain logical dependency.
- Floats Free Float (FF) = delay without affecting next node's EPO. Total Float (TF) = delay without delaying total project completion. Critical Activity has
TF = 0 and FF = 0.
6-Step CPM Procedure: (1) Define activities β (2) Draw logical arrow network β (3) Estimate durations (dummy = 0) β (4) Compute EPO, LPO, EST, EFT, LST, LFT, TF, FF β (5) Identify Critical Activities β (6) Trace Critical Path(s).
Memory Hook: Dummy = Zero Time, Zero Cost, Pure Logic β’ 3 Event Types = Tail, Head, Dual.