Period: Aug 2026 | Owner: product-team | Next report: 2026-08-20 | RAG: Amber
The Q3 Mobile App Launch project is in Amber status. M1 Beta Release (Aug 15) is on-track. M2 Public Launch (Sep 30) is at-risk due to a third-party payment API integration delay. A decision is needed by Aug 8 on whether to descope non-critical features (wishlist + social sharing) to protect the Sep 30 launch date.
| Milestone | Due Date | Status | Days from Aug 1 |
|---|---|---|---|
| M1 — Beta Release | 2026-08-15 | On track | 15 |
| M2 — Public Launch | 2026-09-30 | At risk | 60 |
| M3 — Post-Launch Review | 2026-10-15 | Pending | 75 |
Completed: Feature freeze, initial QA cycle, stakeholder demo Due next: Beta release, integration test unblock, launch readiness review
Third-party API integration delay — Critical
| Decision | Options | Recommendation | Needed by |
|---|---|---|---|
| Descope features for Sep 30 | (A) Full scope, slip to Oct 15; (B) Descope wishlist+social, hold Sep 30 | Option B | 2026-08-08 |
/workspace/milestone_timeline.svg — days from Aug 1 to each target date/workspace/milestone_risk_pie.excalidraw — on-track vs at-risk vs pending/workspace/milestone_quadrant.excalidraw — effort vs impact positioning/workspace/milestone_table.excalidrawhttps://brewpage.app/public/4UEk4TdM3L